SAP
C_TFIN22_64 · Question #39
What are the impacts on an S price controlled material when releasing a material cost estimate? Note: There are 2 correct answers to this question.
The correct answer is B. Existing stock is valuated with the new price. D. New standard price is set. See the full explanation below for the reasoning.
Question
What are the impacts on an S price controlled material when releasing a material cost estimate? Note: There are 2 correct answers to this question.
Options
- APrevious material movements are revaluated.
- BExisting stock is valuated with the new price.
- CMoving average price is adjusted.
- DNew standard price is set.
How the community answered
(57 responses)- A11% (6)
- B84% (48)
- C5% (3)
Community Discussion
No community discussion yet for this question.