What are the prerequisites to calculate overhead costs on an internal order? Note: There are 2 correct answers to this question.
The correct answer is C. Define a costing sheet. D. Assign the costing sheet in the order master data. See the full explanation below for the reasoning.
Question
What are the prerequisites to calculate overhead costs on an internal order? Note: There are 2 correct answers to this question.
Options
- AAssign the costing sheet to the costing variant.
- BDefine an overhead key.
- CDefine a costing sheet.
- DAssign the costing sheet in the order master data.
How the community answered
(32 responses)- A6% (2)
- B16% (5)
- C78% (25)
Community Discussion