You want to define when an action should be processed, for example, 'immediate', 'when saving', or 'using selection report'. Which of the following can you use?

The correct answer is C. Processing time. See the full explanation below for the reasoning.

Question

You want to define when an action should be processed, for example, 'immediate', 'when saving', or 'using selection report'. Which of the following can you use?

Options

  • AStart condition
  • BPost Processing Framework
  • CProcessing time
  • DSchedule condition

How the community answered

(34 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    71% (24)
  • D
    18% (6)