The Remodeling Toolbox allows you to define:
The correct answer is C. Several remodeling steps for an InfoCube without the need to empty this InfoCube. Remodeling steps. See the full explanation below for the reasoning.
Question
The Remodeling Toolbox allows you to define:
Options
- ASeveral subsequent remodeling steps for your most important BI Objects like Queries, InfoProviders
- BA single remodeling step for InfoCubes or DataStore Objects. Before executing the remodeling process
- CSeveral remodeling steps for an InfoCube without the need to empty this InfoCube. Remodeling steps
- DA remodeling rule for a process chain, including an integrated batch process consumption check and
How the community answered
(39 responses)- A3% (1)
- B10% (4)
- C79% (31)
- D8% (3)
Community Discussion