In your project plan, you need to provide some guidelines for your less experienced co-workers regarding input ready queries. Which of the following would be correct? (Choose three)
The correct answer is B. Input ready queries can only write back to Real Time InfoCubes. C. At least one key figure in an input ready query needs to be set to 'data can be changed using user entries D. You have the option to set the query as changeable upon execution or not. See the full explanation below for the reasoning.
Question
In your project plan, you need to provide some guidelines for your less experienced co-workers regarding input ready queries. Which of the following would be correct? (Choose three)
Options
- AInput ready queries require the special variable 'most current data' for the characteristic 'Request ID'.
- BInput ready queries can only write back to Real Time InfoCubes.
- CAt least one key figure in an input ready query needs to be set to 'data can be changed using user entries
- DYou have the option to set the query as changeable upon execution or not.
How the community answered
(66 responses)- A23% (15)
- B77% (51)
Community Discussion