You have created a deadline branch. When the deadline expires, the integration process should be canceled. How can you achieve this using SAP design patterns for integration processes?
The correct answer is B. Insert a control step in the deadline branch that cancels the process. See the full explanation below for the reasoning.
Question
You have created a deadline branch. When the deadline expires, the integration process should be canceled. How can you achieve this using SAP design patterns for integration processes?
Options
- AInsert a control step that raises an alert to inform the administrator to stop the process manually.
- BInsert a control step in the deadline branch that cancels the process.
- CNo action is necessary; the process is canceled automatically once the deadline has expired.
- DInsert a switch to send a message to another integrationprocess to cancel the process.
How the community answered
(32 responses)- A3% (1)
- B75% (24)
- C6% (2)
- D16% (5)