C_TB1200_10 · Question #1
Your company manufactures electronic devices. How would you define a technician employee and a calibration machine in order to plan capacity in the production process?
The correct answer is B. Add a Machine resource master data for the machine. Option B is correct because in production capacity planning (as in SAP Business One), resources used in the manufacturing process are defined using Resource master data, not Item master data. There are two resource types: Machine (for equipment like a calibration machine) and…
Question
Your company manufactures electronic devices. How would you define a technician employee and a calibration machine in order to plan capacity in the production process?
Options
- AAdd an item master data with Items type for the machine Add an item master data with Labor type
- BAdd a Machine resource master data for the machine
- CAdd a Machine resource master data for the machine
- DAdd an item master data for the machine
How the community answered
(21 responses)- A5% (1)
- B81% (17)
- C10% (2)
- D5% (1)
Explanation
Option B is correct because in production capacity planning (as in SAP Business One), resources used in the manufacturing process are defined using Resource master data, not Item master data. There are two resource types: Machine (for equipment like a calibration machine) and Labor (for human workers like a technician) - both are needed here, which is what option B captures.
Option A is wrong because Item master data with "Items" or "Labor" types are used for inventory and purchasing, not for defining production capacity resources. Mixing these concepts would cause capacity planning to fail.
Option C appears to describe only the machine without the Labor resource for the technician, making it incomplete for the full scenario.
Option D is wrong for the same reason as A - Item master data tracks goods and services in inventory, not production resource capacity.
Memory tip: Think "R for Resource, R for Real production." When something does work on the shop floor (a machine runs or a person labors), it needs a Resource master record - not an Item record. Machine resource = equipment; Labor resource = people.
Topics