C_TAW12_750 · Question #221

A development object can be assigned to only one change request.

The correct answer is B. False. See the full explanation below for the reasoning.

Question

A development object can be assigned to only one change request.

Options

  • ATrue
  • BFalse

How the community answered

(26 responses)
  • A
    19% (5)
  • B
    81% (21)