SAP
C_TAW12_71 · Question #409
A custom transparent table was created with delivery class A and a table maintenance view was generated for this table. You change the delivery class to C and the table is activated successfully…
The correct answer is D. Delete the original maintenance view and then create and generate a new one. See the full explanation below for the reasoning.
Question
A custom transparent table was created with delivery class A and a table maintenance view was generated for this table. You change the delivery class to C and the table is activated successfully. What additional steps do you have to complete?
Options
- AMaintain and transport the table using the Maintain Table Views transaction (SM30).
- BActivate and adjust the database.
- CRegenerate the existing maintenance view and adjust the table.
- DDelete the original maintenance view and then create and generate a new one.
How the community answered
(28 responses)- A11% (3)
- B14% (4)
- C4% (1)
- D71% (20)
Community Discussion
No community discussion yet for this question.