What is the order of transport in PBO when a ble control is defined in your nodule pool?
The correct answer is C. Ble control fields followed by the remaining screen fields. See the full explanation below for the reasoning.
Question
What is the order of transport in PBO when a ble control is defined in your nodule pool?
Options
- AScreen fields followed by ble control fields
- BAll fields regardless of ble control definit ion are transported at the beginning of PBO
- CBle control fields followed by the remaining screen fields
- DDictionary Fields followed by Program Fields
How the community answered
(31 responses)- A3% (1)
- B10% (3)
- C84% (26)
- D3% (1)
Community Discussion