nerdexam
SAP

C_TADM70_21 · Question #97

A customer SAP system landscape is made up of several systems, all systems have to be migrated to a different database. System set 1 (ERP): Development, Quality Assurance, Production System set 2…

The correct answer is A. 1 X Development, 2 X Production. See the full explanation below for the reasoning.

Question

A customer SAP system landscape is made up of several systems, all systems have to be migrated to a different database. System set 1 (ERP): Development, Quality Assurance, Production System set 2 (BW): Development, Production. How may system copies are involved for system 2 (BW)?

Options

  • A1 X Development, 2 X Production
  • B2 X Development, 2 X Production.
  • C1 X Development, 1X Quality Assurance, 2 X Production
  • D1 X Development, 2 X Production, homogeneous system copy from production to Quality

How the community answered

(62 responses)
  • A
    77% (48)
  • B
    3% (2)
  • C
    5% (3)
  • D
    15% (9)

Community Discussion

No community discussion yet for this question.

Full C_TADM70_21 Practice