nerdexam
SAP

C_TADM70_21 · Question #131

List down the steps for Optimizing the Export / Import Process? There are 2 correct answers to this question

The correct answer is C. Create separate package files for large tables D. Split existing package files. See the full explanation below for the reasoning.

Question

List down the steps for Optimizing the Export / Import Process? There are 2 correct answers to this question

Options

  • AParallelize export method
  • BTake care of files for import order
  • CCreate separate package files for large tables
  • DSplit existing package files

How the community answered

(58 responses)
  • A
    10% (6)
  • B
    5% (3)
  • C
    84% (49)

Community Discussion

No community discussion yet for this question.

Full C_TADM70_21 Practice