How can you achieve that a change request containing only one ABAP program from the DEV system will be imported into several clients of the QAS system? (More than one answers are true)

The correct answer is B. By using client dependent transport routes. See the full explanation below for the reasoning.

Question

How can you achieve that a change request containing only one ABAP program from the DEV system will be imported into several clients of the QAS system? (More than one answers are true)

Options

  • AIt is impossible to achieve this with TMS
  • BBy using client dependent transport routes
  • CBy using transport target groups
  • DBy defining different consolidation routes pointing from the DEV system to the QAS system

How the community answered

(46 responses)
  • A
    13% (6)
  • B
    76% (35)
  • C
    9% (4)
  • D
    2% (1)