What should be done before releasing a transport request in the development system?
The correct answer is A. Unit testing B. Release of all tasks inside the transport request. See the full explanation below for the reasoning.
Question
What should be done before releasing a transport request in the development system?
Options
- AUnit testing
- BRelease of all tasks inside the transport request
- CInformation of system administration about the released tasks
- DDeletion of tasks inside the transport request
How the community answered
(20 responses)- A75% (15)
- C15% (3)
- D10% (2)
Community Discussion