C_TADM51_74 · Question #123
Which of the following activities are executed by JControl? There are 3 correct answers to this question.
The correct answer is A. Connect to the Central Service Instance. C. Synchronize binaries. D. Start one or more server processes as JLaunch processes. See the full explanation below for the reasoning.
Question
Which of the following activities are executed by JControl? There are 3 correct answers to this question.
Options
- AConnect to the Central Service Instance.
- BIn an AS ABAP+Java (Dual Stack) system: Start the ABAP Dispatcher.
- CSynchronize binaries.
- DStart one or more server processes as JLaunch processes.
- EStart the Java Message service.
How the community answered
(36 responses)- A81% (29)
- B8% (3)
- E11% (4)
Community Discussion