C_TADM51_70 · Question #24
Which of the following statements regarding post-installation activities for SAP ECC 6.0 are true? (Choose two.)
The correct answer is A. The installation check verifies the completeness of the installation. B. Additional space in the database is needed to generate ABAP loads of programs, function modules, and. See the full explanation below for the reasoning.
Question
Which of the following statements regarding post-installation activities for SAP ECC 6.0 are true? (Choose two.)
Options
- AThe installation check verifies the completeness of the installation.
- BAdditional space in the database is needed to generate ABAP loads of programs, function modules, and
- CThe newest Support package level is available with the SAP ECC 6.0 installation. Only the SAP executables
- DSAP recommends creating the first client after the installation using client copy profile SAP_CUST.
How the community answered
(44 responses)- A80% (35)
- C14% (6)
- D7% (3)