Which of the following is the sequence of events for the `Inbound Processing and Receipt Confirmation without WM' process? (Only one answer is correct)

The correct answer is A. Receive advanced shipping notification -> Create inbound delivery -> Post goods receipt -> Send. See the full explanation below for the reasoning.

Question

Which of the following is the sequence of events for the `Inbound Processing and Receipt Confirmation without WM' process? (Only one answer is correct)

Options

  • AReceive advanced shipping notification -> Create inbound delivery -> Post goods receipt -> Send
  • BReceive advanced shipping notification -> Create inbound delivery -> Send proof of delivery ->
  • CCreate inbound delivery -> Post goods receipt -> Track and evaluate procurement process with

How the community answered

(49 responses)
  • A
    78% (38)
  • B
    6% (3)
  • C
    16% (8)