C_SM100_718 · Question #70

Which statement is true?

The correct answer is B. Testing is part of the final preparation and go live phase of the implementation project. See the full explanation below for the reasoning.

Question

Which statement is true?

Options

  • ASAP Solution Manager provides functionality for test management and not for test execution.
  • BTesting is part of the final preparation and go live phase of the implementation project.

How the community answered

(51 responses)
  • A
    22% (11)
  • B
    78% (40)