nerdexam
SAP

C_SIGPM_2403 · Question #63

What elements are part of the official BPMN 2.0 notation? Note: There are 2 correct answers to this question.

The correct answer is A. Pool/ Lane C. Task. Pool/Lane (A) and Task (C) are both official BPMN 2.0 elements defined in the OMG specification. Pools and Lanes are "Swimlane" artifacts used to organize process participants and responsibilities, while Tasks are atomic work activities - a core type of Flow Object. "Additional…

Process Modeling and Documentation

Question

What elements are part of the official BPMN 2.0 notation? Note: There are 2 correct answers to this question.

Options

  • APool/ Lane
  • BAdditional Participant
  • CTask
  • DIT-Systems

How the community answered

(26 responses)
  • A
    92% (24)
  • B
    4% (1)
  • D
    4% (1)

Explanation

Pool/Lane (A) and Task (C) are both official BPMN 2.0 elements defined in the OMG specification. Pools and Lanes are "Swimlane" artifacts used to organize process participants and responsibilities, while Tasks are atomic work activities - a core type of Flow Object. "Additional Participant" (B) is not a BPMN 2.0 concept; participants are represented through Pools, not a separate element category. "IT-Systems" (D) is also not a BPMN element - systems may be depicted as Participants within Pools, but "IT-Systems" has no formal place in the BPMN 2.0 notation.

Memory tip: BPMN 2.0 organizes around three core element categories - Flow Objects (Events, Gateways, Tasks), Connecting Objects, and Swimlanes (Pools, Lanes). If an answer choice matches one of these categories, it's likely correct; invented labels like "Additional Participant" or "IT-Systems" are red herrings.

Topics

#BPMN 2.0#notation elements#Pool#Lane

Community Discussion

No community discussion yet for this question.

Full C_SIGPM_2403 Practice