C_S4FCC_2021 · Question #31
Your consolidation monitor is missing the group share calculation task. How could you correct the issue? Note: There are 2 correct answers to this question.
The correct answer is B. Change a task group C. Assign a different task group to your version. To correct the issue of a missing group share calculation task in the consolidation monitor, you can either change the task group (option B) or assign a different task group to your version (option C). Both of these options will allow you to include the missing task in the…
Question
Your consolidation monitor is missing the group share calculation task. How could you correct the issue? Note: There are 2 correct answers to this question.
Options
- AAdd a custom task based on a BAdI
- BChange a task group
- CAssign a different task group to your version
- DAdd a custom task based on an API
How the community answered
(37 responses)- A11% (4)
- B70% (26)
- D19% (7)
Explanation
To correct the issue of a missing group share calculation task in the consolidation monitor, you can either change the task group (option B) or assign a different task group to your version (option C). Both of these options will allow you to include the missing task in the consolidation
Topics
Community Discussion