C_S4CS_2202 · Question #81
You reviewed the project scope and identified the corresponding resources Based on the SAP Activate methodology, which activities must you perform in the Explorer phase? 2 answers
See the full explanation below for the reasoning.
Question
You reviewed the project scope and identified the corresponding resources Based on the SAP Activate methodology, which activities must you perform in the Explorer phase? 2 answers
Options
- AConduct the Fit to Standard analysis to identify fits gaps and perceived gaps
- BConfigure the organizational structure and chart of accounts in the system
- CUse the Quality system to demonstrate SAP Best Practice processes
- DUse the Starter system to demonstrate SAP Best Practice processes