SAP
C_S4CS_2202 · Question #4
According to the SAP Activate methodology, in what phase is the Fit-to-Standard workshop executed? Please choose the correct answer.
The correct answer is D. Explore. See the full explanation below for the reasoning.
Question
According to the SAP Activate methodology, in what phase is the Fit-to-Standard workshop executed? Please choose the correct answer.
Options
- APrepare
- BDeploy
- CRealize
- DExplore
How the community answered
(31 responses)- A3% (1)
- B19% (6)
- C6% (2)
- D71% (22)
Community Discussion
No community discussion yet for this question.