Which of the following processes can you perform using the Process Purchase Requisitions Centrally app in Central Purchasing (2XT). Note: There are 2 correct answers to this question.

The correct answer is A. Create Purchase Requisition C. Assign Source of Supply. A (Create Purchase Requisition) is correct because the app allows central buyers to manually create purchase requisitions directly within the Central Purchasing hub, not just process inbound ones. C (Assign Source of Supply) is correct because assigning a source of supply…

Professional Services Order and Project Processing

Question

Which of the following processes can you perform using the Process Purchase Requisitions Centrally app in Central Purchasing (2XT). Note: There are 2 correct answers to this question.

Options

  • ACreate Purchase Requisition
  • BImport Purchase Requisitions
  • CAssign Source of Supply
  • DCreate Supply Invoice

How the community answered

(22 responses)
  • A
    86% (19)
  • B
    9% (2)
  • D
    5% (1)

Explanation

A (Create Purchase Requisition) is correct because the app allows central buyers to manually create purchase requisitions directly within the Central Purchasing hub, not just process inbound ones. C (Assign Source of Supply) is correct because assigning a source of supply - such as a contract, purchasing info record, or preferred vendor - is one of the primary functions of this app, enabling buyers to convert PRs into purchase orders.

B (Import Purchase Requisitions) is a distractor: PRs from connected backend systems are automatically replicated to Central Purchasing via the system integration; there is no manual "import" action performed through this app. D (Create Supply Invoice) is wrong because invoice creation belongs to the accounts payable/invoice management process - it is entirely outside the scope of purchase requisition processing and isn't even the correct SAP term (SAP uses "Supplier Invoice").

Memory tip: Think of the app's name literally - it helps you process PRs, which means creating them and acting on them (assigning a source of supply). Anything that comes before (importing data) or after (invoicing) falls outside its scope.

Topics