C_S4CPS_2302 · Question #5
Which activities does the consultant do before the first Fit-to-Standard workshop? Note: There are 2 correct answers to this question.
The correct answer is A. Evaluate the L2 Business-Driven Configuration Questionnaire responses. C. Review the integration requirements collected from the Digital Discovery Assessment. Before the first Fit-to-Standard (FTS) workshop, the consultant's role is preparation and review - not execution. Evaluating the L2 Business-Driven Configuration Questionnaire (BDC) responses (A) is correct because these questionnaires capture the customer's process preferences…
Question
Which activities does the consultant do before the first Fit-to-Standard workshop? Note: There are 2 correct answers to this question.
Options
- AEvaluate the L2 Business-Driven Configuration Questionnaire responses.
- BUpload customer master data in the Starter system using migration templates.
- CReview the integration requirements collected from the Digital Discovery Assessment.
- DDeactivate scope items that are NOT part of the Statement of Work/Digital Discovery Assessment.
How the community answered
(57 responses)- A75% (43)
- B7% (4)
- D18% (10)
Explanation
Before the first Fit-to-Standard (FTS) workshop, the consultant's role is preparation and review - not execution. Evaluating the L2 Business-Driven Configuration Questionnaire (BDC) responses (A) is correct because these questionnaires capture the customer's process preferences and must be analyzed in advance so the consultant can guide the workshop effectively. Reviewing integration requirements from the Digital Discovery Assessment (C) is equally essential, as the DDA surfaces cross-system dependencies that must inform the FTS discussion.
Why B is wrong: Uploading customer master data via migration templates is a data migration activity that occurs in later phases (Realize), not during Prepare/Explore before the first FTS workshop.
Why D is wrong: Deactivating out-of-scope items is a system configuration task performed during the Explore phase (often after or as a result of FTS workshops), not as a pre-workshop prerequisite.
Memory tip: Before the FTS workshop, the consultant only reads - they Review the DDA (C) and Read the BDC questionnaire responses (A). Both are passive analysis tasks. Anything that involves touching the system (uploading data, deactivating items) comes later.