You need to connect the SAP Master Data Governance (MDG) hub system to the system landscape. Which activities do you perform? There are 2 correct answers to this question.

The correct answer is A. Configure data replication to send master data from the SAP MDG hub to connected systems and C. Configure the workflow to distribute the data from SAP MDG to the system landscape. See the full explanation below for the reasoning.

Question

You need to connect the SAP Master Data Governance (MDG) hub system to the system landscape. Which activities do you perform? There are 2 correct answers to this question.

Options

  • AConfigure data replication to send master data from the SAP MDG hub to connected systems and
  • BConfigure the Uls so that systems in the landscape have the same view on the master data
  • CConfigure the workflow to distribute the data from SAP MDG to the system landscape
  • DDefine a process to provide customizing and non-governed reference data to the SAP MDG hub

How the community answered

(41 responses)
  • A
    73% (30)
  • B
    10% (4)
  • D
    17% (7)

Community Discussion