Question

Your overseas vendor informs you that problems have arisen during production and that the defined dates have shifted. The goods you have ordered will not be delivered by ship, as agreed, but by aircraft. How can you take these changes into account?(Choose two)

Options

  • AIn the dateline for seasonal procurement, select another transportation chain with a different
  • BUse SAP Event Management to have the actual data updated for the relevant dates, which will
  • CInsert a new entry for the means of transport "aircraft" in the transportation times table.
  • DIf the delivery date is to be monitored, get the suggestion for a suitable activity in the active