SAP
C_ISR_60 · Question #11
In SAP Retail, you have set fixed order and delivery days for requirements planning for your vendor. Which of the following RP procedures can you use to ensure that the article is considered during…
The correct answer is D. Time-phased with automatic reorder point. See the full explanation below for the reasoning.
Question
In SAP Retail, you have set fixed order and delivery days for requirements planning for your vendor. Which of the following RP procedures can you use to ensure that the article is considered during the next planning run if the stock of the article falls below a defined threshold?
Options
- AForecast-based planning
- BManual reorder point planning
- CAutomatic reorder point planning
- DTime-phased with automatic reorder point
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C10% (3)
- D84% (26)
Community Discussion
No community discussion yet for this question.