C_IEE2E_2404 · Question #39

When running MRP, what setting in the material master determines whether a material will be procured or produced?

The correct answer is B. Procurement type. You've hit your limit · resets 12:50am (America/New_York)

End-to-End Business Processes

Question

When running MRP, what setting in the material master determines whether a material will be procured or produced?

Options

  • AMRP type
  • BProcurement type
  • CPurchasing group
  • DProcessing key

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    91% (29)
  • D
    3% (1)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#material master#procurement type#MRP#make-or-buy decision

Community Discussion

No community discussion yet for this question.