nerdexam
SAP

C_HANATEC_12 · Question #72

Which of the following techniques would you use to upgrade an SAP Hana system and keep the downtime to a minimum? Please choose the correct answer. Response:

The correct answer is C. system replication. See the full explanation below for the reasoning.

Question

Which of the following techniques would you use to upgrade an SAP Hana system and keep the downtime to a minimum? Please choose the correct answer. Response:

Options

  • AStorage replication
  • Bhigh availability
  • Csystem replication
  • Dpartitioning

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    83% (20)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full C_HANATEC_12 Practice