SAP
C_HANATEC_11 · Question #240
You are migrating an SAP ERP system to SAP Hana using the software update manager (SUM) with the database migration option (DMO). What happens during the downtime phase? Please choose the correct…
The correct answer is A. the applications database is migrated to the SAP Hana database. See the full explanation below for the reasoning.
Question
You are migrating an SAP ERP system to SAP Hana using the software update manager (SUM) with the database migration option (DMO). What happens during the downtime phase? Please choose the correct answer. Response:
Options
- Athe applications database is migrated to the SAP Hana database
- Bthe SAP Hana database is upgraded
- Cthe shadow repositories is created on the source database
- Dthe shadow repository is migrated to the SAP Hana database
How the community answered
(44 responses)- A80% (35)
- B11% (5)
- C2% (1)
- D7% (3)
Community Discussion
No community discussion yet for this question.