When SAP Hana is not fully started or it is stopped which service does the SAP Hana Studio use to collect information about the database status Please choose the correct answer. Response:
The correct answer is B. sapsatrtsrv. See the full explanation below for the reasoning.
Question
When SAP Hana is not fully started or it is stopped which service does the SAP Hana Studio use to collect information about the database status Please choose the correct answer. Response:
Options
- AIndex server
- Bsapsatrtsrv
- Csaposcol
- Dname server
How the community answered
(31 responses)- A6% (2)
- B81% (25)
- C10% (3)
- D3% (1)
Community Discussion