You want to update a productive SAP HANA system to the next support package stack (SPS). What are the prerequisites?

The correct answer is B. You performed a backup of the system. C. You know the adm password. D. You planned a business downtime for the system. See the full explanation below for the reasoning.

Question

You want to update a productive SAP HANA system to the next support package stack (SPS). What are the prerequisites?

Options

  • AYou applied the new license key for the new SPS.
  • BYou performed a backup of the system.
  • CYou know the adm password.
  • DYou planned a business downtime for the system.
  • EYou prepared the data and log area in the file system

How the community answered

(66 responses)
  • A
    6% (4)
  • B
    76% (50)
  • E
    18% (12)