SAP
C_HANATEC151 · Question #47
You want to update a productive SAP HANA system to the next support package stack (SPS). What are the prerequisites?
The correct answer is B. You performed a backup of the system. C. You know the adm password. D. You planned a business downtime for the system. See the full explanation below for the reasoning.
Question
You want to update a productive SAP HANA system to the next support package stack (SPS). What are the prerequisites?
Options
- AYou applied the new license key for the new SPS.
- BYou performed a backup of the system.
- CYou know the adm password.
- DYou planned a business downtime for the system.
- EYou prepared the data and log area in the file system
How the community answered
(44 responses)- A18% (8)
- B73% (32)
- E9% (4)
Community Discussion
No community discussion yet for this question.