nerdexam
SAP

C_HANATEC151 · Question #17

Which of the following steps allow you to create a test system (system A) based on a productive SAP HANA standalone system (system B)?

The correct answer is B. Restore a complete database backup from system B to system A. D. Copy the data and log volume files from system B to system A. See the full explanation below for the reasoning.

Question

Which of the following steps allow you to create a test system (system A) based on a productive SAP HANA standalone system (system B)?

Options

  • AExport the data from system B to a file share and import the data to system A.
  • BRestore a complete database backup from system B to system A.
  • CCopy a snapshot from system B to system A.
  • DCopy the data and log volume files from system B to system A.

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    78% (21)
  • C
    7% (2)

Community Discussion