Which of the following steps allow you to create a test system (system A) based on a productive SAP HANA standalone system (system B)?
The correct answer is B. Restore a complete database backup from system B to system A. D. Copy the data and log volume files from system B to system A. See the full explanation below for the reasoning.
Question
Which of the following steps allow you to create a test system (system A) based on a productive SAP HANA standalone system (system B)?
Options
- AExport the data from system B to a file share and import the data to system A.
- BRestore a complete database backup from system B to system A.
- CCopy a snapshot from system B to system A.
- DCopy the data and log volume files from system B to system A.
How the community answered
(27 responses)- A15% (4)
- B78% (21)
- C7% (2)