C_HANATEC151 · Question #124

Which of the following actions are required in the SAP HANA studio to use the Enhanced Change and Transport System (CTS+)?

The correct answer is C. Configure the connection to the CTS in the preferences. D. Use an authorized user to attach SAP HANA content to transport requests. See the full explanation below for the reasoning.

Question

Which of the following actions are required in the SAP HANA studio to use the Enhanced Change and Transport System (CTS+)?

Options

  • ACreate a delivery unit that contains all of the runtime objects.
  • BCreate the HTTP connection named CTSDEPLOY.
  • CConfigure the connection to the CTS in the preferences.
  • DUse an authorized user to attach SAP HANA content to transport requests.

How the community answered

(42 responses)
  • A
    10% (4)
  • B
    19% (8)
  • C
    71% (30)