SAP
C_HANAIMP141 · Question #100
The IT department has a service level agreement (SLA.that states "all production systems must be available to the end user within 1/2 hour of any type of system failure." Which of the following…
The correct answer is D. Scale out high availability. See the full explanation below for the reasoning.
Question
The IT department has a service level agreement (SLA.that states "all production systems must be available to the end user within 1/2 hour of any type of system failure.” Which of the following helps meet the SLA for SAP HANA system failures?
Options
- ADisaster recovery
- BScale up
- CSide-by-side scenario
- DScale out high availability
How the community answered
(29 responses)- A7% (2)
- B14% (4)
- C3% (1)
- D76% (22)
Community Discussion
No community discussion yet for this question.