How can you make sure that a risk analysis is performed when you use access request management? Note: There are 2 correct answers to this question
The correct answer is B. Configure the MSMP workflow stage to require a risk analysis D. Set the Enable Risk Analysis Form on Submission parameter to Yes. See the full explanation below for the reasoning.
Question
How can you make sure that a risk analysis is performed when you use access request management? Note: There are 2 correct answers to this question
Options
- ASet Enable Offline Risk Analysis parameter to Yes
- BConfigure the MSMP workflow stage to require a risk analysis
- CConfigure the MSMP workflow path to require a risk analysis
- DSet the Enable Risk Analysis Form on Submission parameter to Yes
How the community answered
(30 responses)- A10% (3)
- B77% (23)
- C13% (4)