C_EWM_95 Question #232: Real Exam Question with Answer & Explanation
The correct answer is C. You do not require detailed documentation of the kitting procedure in EWM D. You are not performing kitting in one special kitting work centre, but at a work centre where you. See the full explanation below for the reasoning.
Question
You can also create a kit without a VAS order at a work centre. You can configure a work centre where you also pack in such a way that you can confirm generated kits there. This process is suitable for the following cases There are 2 correct answers to this question Response:
Options
- AYou require detailed documentation of the kitting procedure in EWM
- BYou are not performing kitting in one special kitting work centre, but at a work centre where you
- CYou do not require detailed documentation of the kitting procedure in EWM
- DYou are not performing kitting in one special kitting work centre, but at a work centre where you