When you combine the process-oriented control with the layout-oriented storage control, which of the following is true? Please choose the correct answer. Response:
The correct answer is A. SAP EWM always determines the process-oriented storage control first. See the full explanation below for the reasoning.
Question
When you combine the process-oriented control with the layout-oriented storage control, which of the following is true? Please choose the correct answer. Response:
Options
- ASAP EWM always determines the process-oriented storage control first.
- BIt does not matter which type of storage control is determined first.
- CSAP EWM always determines the layout-oriented storage control first.
How the community answered
(21 responses)- A81% (17)
- B14% (3)
- C5% (1)