C_EWM_91 · Question #11
After completing all value-added services, the system moves the products in the following areas There are 2 correct answers to this question. Response:
The correct answer is A. goods issue area B. final storage bin. See the full explanation below for the reasoning.
Question
After completing all value-added services, the system moves the products in the following areas There are 2 correct answers to this question. Response:
Options
- Agoods issue area
- Bfinal storage bin
- CShipping plant
- DFinal Warehouse
How the community answered
(37 responses)- A81% (30)
- C8% (3)
- D11% (4)