Which of the following are features of the Start process in a chain? (2)
The correct answer is A. It is the only process that can be scheduled without a predecessor B. Only one start process is allowed for each process chain. In SAP BW Process Chains, the Start process is a unique initiating element. A is correct because the Start process is the only one that can be scheduled (e.g., via a time-based trigger or immediate start) without requiring another process to precede it - it is the entry point…
Question
Which of the following are features of the Start process in a chain? (2)
Options
- AIt is the only process that can be scheduled without a predecessor
- BOnly one start process is allowed for each process chain
- CIt Can be a Successor of another process
- DIt Can be re-used in other process chains.
How the community answered
(22 responses)- A86% (19)
- C5% (1)
- D9% (2)
Explanation
In SAP BW Process Chains, the Start process is a unique initiating element. A is correct because the Start process is the only one that can be scheduled (e.g., via a time-based trigger or immediate start) without requiring another process to precede it - it is the entry point of the chain. B is correct because each process chain is permitted exactly one Start process; having multiple would create ambiguity about where execution begins.
C is wrong because the Start process cannot be a successor - by definition, it has no predecessor and sits at the top of the chain. D is wrong because the Start process belongs exclusively to its own chain and cannot be referenced or reused in other process chains.
Memory tip: Think of the Start process like the ignition key of a car - there's only one per vehicle (chain), it's what kicks everything off, and you can't share it with another car or put it in the middle of the dashboard.