You want to save a report that you have not run with data. There are no subreports. Which procedure should you use to save the report data?
The correct answer is D. From the Preview tab, select Save Data with Report and save the report. See the full explanation below for the reasoning.
Question
You want to save a report that you have not run with data. There are no subreports. Which procedure should you use to save the report data?
Options
- AFrom the Preview tab, select Save As and save the report.
- BFrom the Design tab, select Save As and save the report.
- CFrom the Design tab, select Save Data with Report and save the report.
- DFrom the Preview tab, select Save Data with Report and save the report.
How the community answered
(33 responses)- A3% (1)
- B9% (3)
- C18% (6)
- D70% (23)
Community Discussion
No community discussion yet for this question.