A schedule request for a Crystal report is sent to the Central Management Server (CMS). Which task does the CMS perform next?
The correct answer is B. Add a record with the schedule information to the system database. See the full explanation below for the reasoning.
Question
A schedule request for a Crystal report is sent to the Central Management Server (CMS). Which task does the CMS perform next?
Options
- AAssign the request to a job server.
- BAdd a record with the schedule information to the system database.
- CRequest the report from the Input File Repository Server.
- DSend the report instance to the Output File Repository Server.
How the community answered
(26 responses)- A4% (1)
- B81% (21)
- C4% (1)
- D12% (3)