A schedule request for a Crystal report is sent to the Central Management Server (CMS). Which task does the CMS perform next?

The correct answer is B. Add a record with the schedule information to the system database. See the full explanation below for the reasoning.

Question

A schedule request for a Crystal report is sent to the Central Management Server (CMS). Which task does the CMS perform next?

Options

  • AAssign the request to a job server.
  • BAdd a record with the schedule information to the system database.
  • CRequest the report from the Input File Repository Server.
  • DSend the report instance to the Output File Repository Server.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    81% (21)
  • C
    4% (1)
  • D
    12% (3)