SAP
C_ARP2P_2002 · Question #107
C_ARP2P_2002 Question #107: Real Exam Question with Answer & Explanation
The correct answer is C. The buyer informs the supplier outside of the system.. See the full explanation below for the reasoning.
Question
How is a receipt rejection communicated to the supplier? Please choose the correct answer.
Options
- AA new version of the purchase order is generated.
- BAriba Network sends a notification when the next receiving task is run.
- CThe buyer informs the supplier outside of the system.
- DThe rejected quantity is updated on the ship notice.
Community Discussion
No community discussion yet for this question.