C_ACTIVATE12 · Question #91

In Which phase does the Transition to Operations work stream start? Please choose the correct answer. Response:

The correct answer is C. Deploy. See the full explanation below for the reasoning.

Question

In Which phase does the Transition to Operations work stream start? Please choose the correct answer. Response:

Options

  • AExplore
  • BRealize
  • CDeploy
  • DPrepare

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    15% (7)
  • C
    73% (35)
  • D
    8% (4)