SAP
C_ACTIVATE12 · Question #85
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 3 correct answers to this question. Response:
The correct answer is B. Custom code adjustment C. Delta configuration D. Development system migration. See the full explanation below for the reasoning.
Question
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 3 correct answers to this question. Response:
Options
- AOperations impact analysis
- BCustom code adjustment
- CDelta configuration
- DDevelopment system migration
- ESandbox system migration
How the community answered
(53 responses)- A17% (9)
- B75% (40)
- E8% (4)
Community Discussion
No community discussion yet for this question.