C_ACTIVATE12 · Question #80
In which phase do you create a prioritized list of user requirements? Please choose the correct answer. Response:
The correct answer is B. Explore. See the full explanation below for the reasoning.
Question
In which phase do you create a prioritized list of user requirements? Please choose the correct answer. Response:
Options
- ARealize
- BExplore
- CPrepare
- DDeploy
How the community answered
(25 responses)- A4% (1)
- B76% (19)
- C16% (4)
- D4% (1)