What technique helps agile project teams to prioritize a large, flat backlog? Please choose the correct answer. Response:
The correct answer is B. User Story Mapping. See the full explanation below for the reasoning.
Question
What technique helps agile project teams to prioritize a large, flat backlog? Please choose the correct answer. Response:
Options
- AFit/Gap Analysis
- BUser Story Mapping
- CRetrospective
- DPlanning Poker
How the community answered
(30 responses)- A3% (1)
- B80% (24)
- C3% (1)
- D13% (4)