SAP
C_ACTIVATE12 · Question #66
Who determines the priority of user stories in the backlog of an Agile project? Please choose the correct answer. Response:
The correct answer is D. Product Owner. See the full explanation below for the reasoning.
Question
Who determines the priority of user stories in the backlog of an Agile project? Please choose the correct answer. Response:
Options
- AProject Manager
- BProject Team
- CSCRUM Master
- DProduct Owner
How the community answered
(25 responses)- A8% (2)
- B12% (3)
- C4% (1)
- D76% (19)
Community Discussion