C_ACTIVATE12 · Question #58

In which SAP Activate methodology phase does the team complete the Transformation Strategy? Please choose the correct answer.

The correct answer is A. Prepare. See the full explanation below for the reasoning.

Question

In which SAP Activate methodology phase does the team complete the Transformation Strategy? Please choose the correct answer.

Options

  • APrepare
  • BExplore
  • CRealize
  • DDeploy

How the community answered

(41 responses)
  • A
    80% (33)
  • B
    5% (2)
  • C
    2% (1)
  • D
    12% (5)